Skip to main content

All Projects
This document summarizes the status of technical services projects that are currently in progress. For information about projects that are inactive or completed, see LTS Completed or Inactive Projects.
For explanations of priorities, see Priority definitions

Dpt Sub Dpt Project Name Priority Target Date Contact Other Contributors Notessort icon
ERSM License Review -- Image Collections 3-On hold ? Bill Kara
ERSM ERM License scanning and links to lists 2-In Process 2009-06-01 Liisa Mobley Adam Chandler
MDS EAD/Archivists' Toolkit implementation 3-On hold 2010-06-30 Glen Wiley, Liz Muller Sarah Keen, Eli Brown
MDS Re-design and documentation to logs.library.cornell.edu 2-In Process 2009-06-01 Nancy Solla, Glen Wiley Adam Chandler
Acq Obtaining MARC records for Eastview approvals 2-In Process Pedro Arroyo
Cat Hatch gift 3-On hold 2009-06-30 Jim Alberts

30 added vols and 1,000+ cassette tapes in SE Asian languages.

Cat Montes collection (urban architecture) 1-High 2012-07-31 Margaret Nichols

About 2,000 vols., mostly with cataloging copy

DMS-BP t8 903 Field Cleanup 3-On hold 2010-06-30 Gary Branch Pete Hoyt

After Microsoft and Google project, there are bibliographic records with a plethora of 903...

MDS Parmenter grant 2-In Process 2010-06-15 Liz Muller Fiona Patrick, Peter Hirtle, Dean Krafft, Jon Parmenter

Apply for grant to digitize and transcibe Native American manuscript records.  Goal is to...

Acq-Cat Knight Visual Resources Transfer to Fine Arts Library 3-On hold 2010-12-31 Pedro Arroyo Pam Stansbury

Approx. 850 DVDs (more items possible later) to be processed for Fine Arts Library. ...

DMS Asia Pamphlet Withdrawal Project 3-On hold 2010-06-30 Barb Tarbox

Asia copy 2's Pamphlet with olin,str1 Voyager location for withdrawal. Approx. 925 volumes to be...

MDS Acquisitions workflow analysis 2-In Process 2009-12-31 Glen Wiley, Liz Muller, Dianne Dietrich Boaz Nadav-Manes

Assess departmental workflows and communications/management tools.  Create document...

DMS Retrospective Barcoding: Kroch serials 2-In Process 2010-06-30 Barb Tarbox, Sally Lockwood

Barcoding of, and item creation for all remaining unbarcoded serial volumes in Kroch library (...

DMS-BP e7 ITSO Summary Report Rewrite 2-In Process 2010-02-28 Natalya Pikulik, Gary Branch Pete Hoyt, Boaz Nadav-Manes

Boaz would like a reworking of the summary report so that an order assistant needs to only look...

Cataloging Bound 19th cent. sheet music 2-In Process 2010-06-01 Jim Alberts

ca. 100 bound volumes to be cataloged for Music Locked Press

Cat Music Library Bound Sheet Music Collection 2-In Process 2010-31-8 Jim Alberts

ca. 200 binder's collections with 30-40 pieces of sheet music bound in each; cataloged as bound-...

Acq-Cat Small Gifts from various Departments 2-In Process 2009-10-30 Pedro Arroyo

Coincidental receipt of several small gifts  (<100) within a short period from...

Acq Complete MSO purchase orders in Voyager 2-In Process 2010 Boaz Nadav-Manes, Natalya Pikulik

Complete all cancelled MSO orders in Voyager, close the checkin patterns and update notes

DMS-BP g7 LSDI Google: Conversion of Pick Lists III 3-On hold 2009-12-24 Gary Branch Pete Hoyt, Jim LeBlanc, Joy Paulson, Lydia Pettis, Barb Tarbox

Conversion of Google pick lists to CUL-type pick lists for non-life science libraries.  We'...

MDS Registry of Digital Collections improvements 2-In Process 2009-12-31 Liz Muller Rick Silterra

Coordinate additions/improvements to Registry back end.  See...